Products, Vendors, CAD Files, Spec Sheets and More...
Sign up for LAWeekly newsletter
When the City of Petoskey needed to build a 1.3-mile section of asphalt bike path on the edge of a Lake Michigan bluff, they required a system to maintain the structural stability of the slope above and below the path.
Because the trail is along one of the most scenic areas of the route, designers needed a retaining wall that would not only provide a structural solution, but an aesthetic solution as well.
‘’We considered spanning the area with a bridge structure but found it too expensive,’’ said Lucas Porath, P.E. with Northwest Design Group in Petoskey. ‘’We also considered using natural stone, but again, Rosetta was the more economical option.’’
Rosetta Hardscapes Outcropping Collection retaining walls are more economical primarily due to their dimensional consistency, which translates into saved installation time. Where natural stone often requires sorting and cutting to make each piece fit correctly, these large blocks are manufactured from precast concrete. ‘’We were trying to match the natural landscape so we needed a fairly massive product to match the scale of the project,’’ said Al Hansen, director of the City of Petoskey’s Parks and Recreation department.
The molds for the block system are taken from heavily weathered natural limestone, which gives the blocks the look of natural stone. The blocks come in different shapes and heights, giving walls a random look but keeping design and installation easy. The blocks are also manufactured with integral color; in this case the company’s ‘’Lakeshore Blend’’ pallet was chosen to complement the rock indigenous to the area. ‘’It kind of blends into the actual material that surrounds it; it is irregular and looks more like natural limestone than a regular concrete retaining wall. We’ve used it in several other applications along the path because we like the look,’’ Hansen said.
H&D, a division of Reith-Riley Construction Co., Inc., of Bay Shore, Michigan installed the walls. The five-man H&D crew consisted of an operator for the backhoe, an operator for the skidsteer, two laborers and a foreman. ‘’The biggest challenge for this project was accessibility. Unfortunately, we were on the railroad grade and the entire grade was only 13 ft. wide before it dropped off into the lake. We had to stage everything quite a ways back and bring the blocks in one pallet at a time,’’ said H&D foreman Mark Wagner.
Wagner explained that his crew brought the blocks down one pallet at a time and placed them using a backhoe and the Rosetta lifting device. Due to the massive size of each block, installation progressed quickly.
To prepare the base, the foundation soil was compacted and the crew installed a four-inch perforated sock drain pipe at the back of the excavated trench. The drain was daylighted below and away from the wall. The crew then installed a stone leveling pad.
The design of the lower section of the project called for an 18 ft. tall wall at the highest point, so reinforcement was necessary. The wall was reinforced using both Paraweb strap and geogrid. The walls above the bike path were gravity walls and utilized a cast-in-place concrete backfill design where stability needed to increase.
Since hydrostatic pressure is the number one cause of retaining wall failure, installing drains and backfill as specified by the engineer was a critical step in keeping backfill materials dry and structurally sound.
Because the bike path is situated 20-30 ft. above the beach, lake access required a staircase. The city chose to use Rosetta’s line of ‘’irregular’’ steps because the steps have a natural stone shape and look, but have the height consistency of a manufactured product. The consistent rise of each step allows for fast installation and also safe access for pedestrians.
The entire project, including the 5,200 sq. ft. of retaining wall, was completed in about two months. This newest section of the bike path is considered the ‘’crown jewel’’ of the 23 mile path and has seen heavy use from bikers and pedestrians since it was dedicated on June 20, 2009. ‘’The walls have been very well received,’’ Porath said.
Francisco Uviña, University of New Mexico
Hardscape Oasis in Litchfield Park
Ash Nochian, Ph.D. Landscape Architect
November 12th, 2025
Sign up to receive Landscape Architect and Specifier News Magazine, LA Weekly and More...
Invalid Verification Code
Please enter the Verification Code below
You are now subcribed to LASN. You can also search and download CAD files and spec sheets from LADetails.