Products, Vendors, CAD Files, Spec Sheets and More...
Sign up for LAWeekly newsletter
Renovating the hardscape of a historical landmark requires diligence and attention to detail. John Girzadas, Executive Vice President of Burling Builders, Inc., discusses overcoming challenges and working with subcontractors on the hardscape installation of the historic Buckingham Fountain in Chicago.
A historical landmark is a direct link to the history of a city and its inhabitants, so keeping an important landmark in first-rate condition is a way that the present can honor the important people and events of its past. Properly renovating a historical area means dedicating the time and hard work necessary toward honoring the landmark's significance. The Buckingham Fountain, a prominent city memorial in Chicago, underwent a major renovation process on its hardscapes.
The Buckingham Fountain is placed in Chicago's Grant Park, a park that is referred to as the city's ''front yard.'' The fountain was the work of architect-planner Edward H. Bennett, a significant figure in the creation and execution of the 1909 Plan of Chicago, the plan that was instrumental in the creation of lakefront amenities. Since Buckingham Fountain's opening in 1927, the fountain has been one of Chicago's most popular attractions.
Although the fountain is one of the city's most recognized landmarks, the rough winters and numerous freeze-thaw cycles have inflicted considerable damage. In 2008, the Chicago Park District implemented a $25 million restoration and renovation project for the fountain.
The company in charge of the general contracting work for the Buckingham Fountain project was Burling Builders, Inc., a Chicago-based company that has been doing contractor work for about thirty years. ''We do [both] government and private commercial projects in the Chicagoland area,'' said John Girzadas, Executive Vice President of Burling Builders.
Installing the hardscapes for a historic landmark required a different approach from projects that do not have that same historical significance. ''All of the products had to be approved by the Historic Landmark Committee to make sure that they were appropriate for the project,'' said Girzadas.
Since the Chicago Park District wished for the restoration to be as close to the original fountain's work as possible, attention was paid to every detail of the project. The Park District, working with the architect of the project, selected the materials for the hardscapes before putting the public bid together. ''A lot of the material selection they were really diligent about,'' said Girzadas.
The Chicago Park District purchased the permeable pavers directly from Unilock, a paving stone manufacturer. The Eco-Priora Coral Gem pavers closely matched the original fountain paving color and appearance. ''There used to be crushed granite stone chips in the plaza that were pink in color, so the pavers were intended to mimic that,'' said Girzadas. ''They [also] wanted the permeable pavers set in a manner that the eye could not easily distinguish a pattern.'' All the pavers were hand set in a 5 ft. by 5 ft. block.
Properly installing the 140,000 square feet of pavers that were needed for the hardscapes was a difficult procedure. ''It's not every day you put down 140,000 square feet of pavers,'' said Girzadas. ''It challenged even the manufacturer and paver installer.'' Transporting the paver products and materials to the work site also presented its own set of problems. ''Getting the pavers into an urban environment and historic location were also challenges that were there,'' said Girzadas. Since the site is surrounded by four busy streets and there was access only from one side, the installer had to stage the deliveries in the morning to avoid rush hour traffic. Once the pavers and materials were in place, the installers then went about laying the pavers. It took over 50 deliveries to transport all the materials to the site (which amounted to about 20-30 days), and installation took place while the materials continued to be delivered.
In addition to the hardscape installation, Burling Builders performed other tasks for the Buckingham Fountain renovation. ''We did the pavers, all the site removals, installed a hundred or so park benches, new lighting, installed some new stairs, handicap ramps, extensive re-work of the landscape,'' said Girzadas. And then the precast that was selected for the stairs needed to be matched to the old roof structure of the old pumphouse.''
One of the major difficulties of installing the hardscapes for Buckingham Fountain was working through winter. Burling Builders began the project in the first week of September 2008 and ended in March 2009, so the company did most of the project during the harsh conditions of a Chicago winter. ''I would say that working through the winter was the most difficult challenge we faced,'' said Girzadas. ''Keeping the ground thawed and the work area cleared of snow and ice so we could continue the paver operation was quite a challenge.'' To address this problem, they used ground thaw machines, which have a radiant hose system that is spread on the ground, covered with blankets and sits on the ground for 24 hours to keep everything thawed.
The experience of the professionals who installed the hardscapes was invaluable for the hardscape renovation. ''The experience of the installer of the pavers [LPS Pavement] was irreplaceable,'' said Girzadas. ''They really understood [the installation] and worked with everybody on how to do it.'' The hard work and cooperation between all the participants of the Buckingham Fountain project made the installation process successful. ''We all worked on the plan together and we all followed it,'' said Girzadas.
The Buckingham Fountain's renovation ensures that future generations of Chicago residents and tourists will continue to enjoy this piece of the city's history.
Raleigh, North Carolina
Francisco Uviña, University of New Mexico
Hardscape Oasis in Litchfield Park
Ash Nochian, Ph.D. Landscape Architect
Sign up to receive Landscape Architect and Specifier News Magazine, LA Weekly and More...
Invalid Verification Code
Please enter the Verification Code below
You are now subcribed to LASN. You can also search and download CAD files and spec sheets from LADetails.